SOLUTION: In a factory , 10 workers were engaged to finish a piece of work in a certain number of days. however if one worker is dropped everyday , except the first day it will take one more

Algebra.Com
Question 903776: In a factory , 10 workers were engaged to finish a piece of work in a certain number of days. however if one worker is dropped everyday , except the first day it will take one more day to finish the work. the number of days in which the work was to be completed are
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
they were contracted to finish in 4 days 10*4=40 man days
but it took 5 days since they lost a worker every day
so on the 4th day
day workers man days
1 10 10
2 9 19
3 8 27
4 7 34
5 6 40
equivalent to 10 workers for 4 days

RELATED QUESTIONS

A certain number of men can finish a piece of work in 10 days. If however there were 10... (answered by ankor@dixie-net.com)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)
in a factory one out of every 9 is a female worker. If the number of female workers is... (answered by John10)
twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop... (answered by Alan3354)
300 men were engaged to complete a job in a certain number of days. But due to another... (answered by richwmiller)
300 men were engaged to complete a job in certain number of days. but due to another... (answered by richwmiller)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
When workers A and B work together, they can finish the flooring of a house in 6... (answered by josgarithmetic,stanbon)
28 workers can finish a piece of work in 45 days. a)How many workers are needed if the... (answered by richwmiller,rothauserc)