SOLUTION: An operation has a 5 percent scrap rate. As a result, only 88 good pieces per hour are produced. What is the potential increase in labour productivity that could be achieved by eli
Question 1185408: An operation has a 5 percent scrap rate. As a result, only 88 good pieces per hour are produced. What is the potential increase in labour productivity that could be achieved by eliminating the scrap? Answer by ikleyn(52752) (Show Source): You can put this solution on YOUR website! .
0.95x = 88
x = = 92.63 pieces.
Next you round the decimal to the maximum smaller integer number,
obtaining the ANSWER : 92 pieces.