SOLUTION: if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Algebra
->
Algebra
->
Percentages: Solvers, Trainers, Word Problems and pie charts
->
Lessons
-> SOLUTION: if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Log On
Ad:
Algebra Solved!™
: algebra software solves algebra homework problems with step-by-step help!
Ad:
Algebrator™
solves your algebra problems and provides step-by-step explanations!
Algebra: Percentage and Pie Charts
Solvers
Lessons
Answers archive
Quiz
In Depth
If you need
immediate math help from PAID TUTORS right now
, click here
. (paid link)
Click here to see ALL problems on percentage
Question 242438
:
if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Answer by
JimboP1977(308)
(
Show Source
):
You can
put this solution on YOUR website!
Well the days are increasing by a 1/3 so you need a third less men to do the work. Therefore it is 4 men.