SOLUTION: Ten workers could do the job in 12 days. If 8 workers worked for 5 days and then half of them quit, how long would it take for the rest to complete the job?

Algebra.Com
Question 66858This question is from textbook Advanced mathematics
: Ten workers could do the job in 12 days. If 8 workers worked for 5 days and then half of them quit, how long would it take for the rest to complete the job? This question is from textbook Advanced mathematics

Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Ten workers could do the job in 12 days.
This means the job requires 10*12 = 120 man/days to complete
:
If 8 workers worked for 5 days and then half of them quit, how long would it take for the rest to complete the job?
:
I understand this to mean how many more days will be required after half of them quit. Let x = number of more days required:
:
original group + half the group = 120 man/days
(8*5) + 4x = 120
40 + 4x = 120
4x = 120 - 40
4x = 80
x = 20 days to complete the job:
:
Check: (8*5) + (4*20) = 120 man/days

RELATED QUESTIONS

Two workers, if they were working together could finish a job in 12 days. If one worker... (answered by josgarithmetic)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
There was 12 workers and to complete the job will take 5 weeks and each week is 5 days... (answered by josgarithmetic,ptaylor,MathTherapy)
Three workers can do a job in 12 days. Two of the workers work twice as fast as the... (answered by josgarithmetic)
If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)
If M workers can do a job in D days, how long would it take 40 workers to do the same... (answered by ptaylor)
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
Working together, 4 skilled workers can complete a job in 5 days. However, 5 semi-skilled (answered by ankor@dixie-net.com)
It takes 4 workers 42 days to complete a job. If 2 of the workers only work half days,... (answered by addingup,ikleyn)