SOLUTION: A team of 2 men and 5 women completed one –fourth of a job in 3 days. After 3 days another man joined the team and they took 2 days to complete another one –fourth of the job. How

Algebra.Com
Question 933854: A team of 2 men and 5 women completed one –fourth of a job in 3 days. After 3 days another man joined the team and they took 2 days to complete another one –fourth of the job. How many men can complete the whole job in 4 days?
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
A team of 2 men and 5 women completed one –fourth of a job in 3 days. After 3 days another man joined the team and they took 2 days to complete another one –fourth of the job. How many men can complete the whole job in 4 days?
----
Let:
men rate = m
woman rate = w
----
2m + 5w = 1/12
3(2m+5w) + 2(3m+5w) = 1/2
----
3(1/12) + 2(m+(1/12)) = 1/2
1/4 + 2m + (1/6) = 1/2
2m + (5/12) = 6/12
2m = 1/12
m = 1/24
----
One man can do the job in 24 days.
6 men can do the job in 4 days.
----
cheers,
Stan H.
----------------

RELATED QUESTIONS

Hi one team of workers completes a job in 10 days, while another team completes it in... (answered by greenestamps,josgarithmetic,ikleyn)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were... (answered by josgarithmetic)
4 men and 10 women were put on a work. They completed 1/3 of the work in 4 days. After... (answered by josgarithmetic)
3 men can do the job of 4 women. If 3 men can do a job in 8 days, in how many days can 5... (answered by richwmiller)
16 men can finish a work in 12 days. After they worked for 4 days, some more men joined... (answered by ikleyn,josgarithmetic)
i'm having a hard time on solving this problem: A group of workers can do a job in 8... (answered by ankor@dixie-net.com)
A painting job can be completed by 3 painters in 17 days. If 12 more painters join the... (answered by josmiceli)
a painting job can be completed by 7 painters in 17 days. if 21 more painters joined the... (answered by ankor@dixie-net.com)