Question 128149: 20 men finished 1/4 of the house in 7 days.but they have to finish it in 5 more days. how many men shall be added to the crew so that they can finish the house?
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
20 men finished 1/4 of the house in 7 days.but they have to finish it in 5 more days. how many men shall be added to the crew so that they can finish the house?
----------------------------
# of men and # of houses completed are directly related
# of men and # of days required are inversely related
--------------
General Equation:
men = k[h/d]
Need to find "k"
---------------
Your problem:
20 = k[(1/4)/7]
k = 28*20 = 560
-----------------
Your Equation:
m = 560[h/d]
Substitute your given values of h= 3/4 of a house and d = 5 days
to get:
m = 560[(3/4)/5]
m = 140*3/5
m = 28*3
m = 84 (# of men to complete 3/4 th of the house in 5 days)
==============
Cheers,
Stan H.

RELATED QUESTIONS

18 men can dig a ditch in 10 days. After they have worked for 4 days how many more men... (answered by ankor@dixie-net.com)
1. Ten men can paint a house in 3 days. In how many days can 5 men finish the same job?... (answered by josmiceli)
A certain number of men can finish a piece of work in 10 days. If however there were 10... (answered by ankor@dixie-net.com)
twelve men can finish the job in 20 days. Five men were working at the start and after 10 (answered by lwsshak3)
A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were... (answered by josgarithmetic)
20 men decided to repair a house in 30 days . But after 6 days 8 men fell sick . How many (answered by ankor@dixie-net.com,josgarithmetic)
A and B working together can finish the job in 10 days. if A works 4 days and B works 3... (answered by josgarithmetic,ikleyn)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men... (answered by josgarithmetic)