Question 1167923: One roofer can put a new roof on a house three times faster than another. Working together they can roof a house in 5 days. How long would it take the faster roofer working alone?
Answer by Theo(13342)   (Show Source): You can put this solution on YOUR website!
rate * time = quantity.

let x = the rate of the slower roofer.

then 3x = the rate of the faster roofer.

when they work together their rates are additive and they can roof a house in 5 days.

quantity = 1 roof

formula becomes:

(x + 3x) * 5 = 1
combine like terms to get:
4x * 5 = 1
simplify to get:
20x = 1
solve for x to get:
x = 1/20

that's the rate of the slower roofer.

the rate of the roofer is 3 times that = 3/20 of the job per day.

when the faster roofer is working alone, the equation becomes:

3/20 * time = 1

solve for time to get:

time = 20/3

the faster roofer, working alone, can roof a house in 20/3 days.

that would be 6 and 2/3 days.

that should be your answer. *****

to go a few steps further, .....

when the slower roofer works alone, the formula becomes:

1/20 * time = 1

solve for time to get:

time = 20 days.

the faster roofer completes the job in 6 and 2/3 days, working alone.
the slower roofer completes the job in 20 days, working alone.

it takes the slower work 3 times as long to complete the job as the faster worker.

that's because the faster worker is 3 times as fast as the slower worker.

everything checks out.

your solution is good.

RELATED QUESTIONS

one roofer can put a new roof on a house three times faster than another. working... (answered by ikleyn)
one roofer can put a new roof on a house three times faster than another. Working... (answered by chosenpoint)
one roofer can put a new roof on a house three times faster than another. Working... (answered by edjones)
One roofer can put a new roof on a house three times faster than another. Working... (answered by josgarithmetic,ikleyn,greenestamps)
One roofer can put a neew roof on a house three times faster than another. Working... (answered by stanbon,checkley71)
If one professional roofer can roof and house in six days and another roofer can do it in (answered by ptaylor)
an experienced roofer can work twice as fast as helper. working together, they can... (answered by Boreal)
An experienced roofer can roof a house in 26 hours. A beginning roofer needs 39 hours to... (answered by solver91311)
working together, it takes two roofers 4 hours to put a new roof on a portable classroom. (answered by scott8148)