SOLUTION: A and B working together can complete a job in 30 days. After they had both worked 18 days, however, A left and B finished the work in 20 more days. Find the time in which each can

Algebra.Com
Question 1121174: A and B working together can complete a job in 30 days. After they had both worked 18 days, however, A left and B finished the work in 20 more days. Find the time in which each can do the work alone.
Found 2 solutions by ankor@dixie-net.com, ikleyn:
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
A and B working together can complete a job in 30 days.
After they had both worked 18 days, however, A left and B finished the work in 20 more days.
Find the time in which each can do the work alone.
:
let a = time A required to complete the job alone
let b = time for B alone
let the completed job = 1
:
Write an equation for each statement
"A and B working together can complete a job in 30 days."
+ = 1
multiply eq by ab
30b + 30a = ab
"After they had both worked 18 days, however, A left and B finished the work in 20 more days."
+ = 1
18b + 38a = ab
:
ab = ab therfore
18b + 38a = 30b + 30a
38a - 30a = 30b - 18b
8a = 12b
a = b
a = 1.5b
:
Using the first equation, replace a with 1.5b
+ = 1
multiply by b
+ 30 = b
20 + 30 = b
b = 50 hrs B working alone
then find a
1.5(50) = 75 hrs b working alone

Answer by ikleyn(52787)   (Show Source): You can put this solution on YOUR website!
.
After A and B worked 18 days together, they made  =  of the job;  so,   of the job remained.


Then B completed this   of the job in 20 days - so, his rate of work is   =  =  of the job per day.


Thus they both have the combined rate of work    of the job per day working together, and the B's individual rate of work is  . 


Hence, the A's rate of work is   -  =  -  =  = .


Answer.  A can do the job in 75 days working alone.


         B can do the job in 50 days working alone.

Solved.


RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A can do a job in 6 days while B can do a job in 8 days. They worked together for 2 days... (answered by richwmiller)
A and B working together can finish the job in 10 days. if A works 4 days and B works 3... (answered by josgarithmetic,ikleyn)
2 persons a and b they can complete a certain work in 16 and 20 days they work together... (answered by anand429)
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
When A,B and C work together, they can finish installing the garden in 3 days. The job... (answered by ikleyn)
If A works alone, he would take 4 days more to complete the job than if both A and B... (answered by josmiceli)
A can complete a job in 9 days, B can do the same job in 10 days and C can do it in 15... (answered by richwmiller)
Please help me solve this problem... i need it rn When john and marsha worked... (answered by stanbon)