SOLUTION: A contractor undertook a certain work to be done in 80 days and employed 72 men to do it. After 20 days he found that 1/3rd of the work has been finished. How many men should he di

Algebra.Com
Question 887057: A contractor undertook a certain work to be done in 80 days and employed 72 men to do it. After 20 days he found that 1/3rd of the work has been finished. How many men should he dismiss in order that the work may be finished on the date agreed upon ?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
A contractor undertook a certain work to be done in 80 days and employed 72 men to do it.
After 20 days he found that 1/3rd of the work has been finished.
How many men should he dismiss in order that the work may be finished on the date agreed upon?
:
Find how many man-days when 72 men work 20 days
20 * 72 = 1440 man-days to do 1/3 of the job
:
2/3 of the job remains to be done, find how many days that requires
2 * 1440 = 2880 man-days
:
The contractor has 60 days left to finish the job.
Find how many men (m) needed, to complete 2880 man-days in 60 days
60m = 2880
m = 2880/60
m = 48 men required
:
Find how many can be laid off
72 - 48 = 24 men

RELATED QUESTIONS

A contractor undertook to build a road in 200 days he employed 140 men after 60 days he... (answered by josgarithmetic,josmiceli,ikleyn,MathTherapy)
A contractor undertook to build a building in 52 days and employed 24 men to work. Only... (answered by ankor@dixie-net.com,josgarithmetic)
A contractor undertook to do a certain piece of work in 9 days. He employed certain... (answered by ikleyn,Theo,greenestamps,josgarithmetic,Edwin McCravy)
a contractor got a contract to build a building in 30 days and employed 20 men to do the... (answered by ankor@dixie-net.com)
A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men.... (answered by macston)
A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were... (answered by josgarithmetic)
a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work... (answered by josgarithmetic)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)