SOLUTION: It takes 10 days for 4 men working 6 hours a day to complete some work. How many days will 3 men working 8 hours a day take to complete the same work?

Algebra.Com
Question 946457: It takes 10 days for 4 men working 6 hours a day to complete some work. How many days will 3 men working 8 hours a day take to complete the same work?
Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
Look at the time in hours for 1 job. Each man has the rate of r job per hours.

For n men working the rate is n*r.

Handle the question first by looking for how many hours for the three men.
, for the one job, and this must be the same quantity of job as .

Remember, for now, t is how many HOURS of work.
;


, HOURS.

This is 10 days, because as given, 8 hours per day.

RELATED QUESTIONS

10 men working for 5 hours a day for 6 days mow an area of 5 acres. If there are 8 men... (answered by josmiceli)
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 (answered by vksarvepalli)
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
If 10 men working 8 hours a day take 15 days to complete a job.How long will it take 20... (answered by lwsshak3)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
Thirty men take 20 days to complete a job working 9 hours a day. How many hours a day... (answered by ankor@dixie-net.com)
Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many... (answered by robertb,MathTherapy)
25 men take 20 days working 8hours a day to complete a job.how many days will 15 men take (answered by ptaylor)
It takes 6 days to clean a house working 4 hours per day. How many days will it take to... (answered by Fombitz)