SOLUTION: Four men working together can dig a ditch in 42 days. They begin, but one man works only half-days. How long will it take to complete the job? -- The answer is 48 days, but how d

Algebra.Com
Question 397884: Four men working together can dig a ditch in 42 days. They begin, but one man works only half-days. How long will it take to complete the job?
-- The answer is 48 days, but how do I get there? Been a 10+ years since I've done a problem like this. Thank you!

Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Four men working together can dig a ditch in 42 days.
Find the number of man-days to complete the job
4*42 = 168 man-days
:
They begin, but one man works only half-days.
How long will it take to complete the job?
Let d = no. days to complete the job
d(3 + .5) = 168
3.5d = 168
d =
d = 48 days

RELATED QUESTIONS

Four men working together can dig a trench in 42 days. They begin the job, but one worker (answered by josmiceli)
A man can dig a ditch in 3 hours and his daughter can dig the same size ditch in 5 hours. (answered by checkley79)
Marlo dug a ditch in one hour and his daughter, Maeryll, can dig the same size ditch in... (answered by Boreal)
Marlo can dig a ditch in 2 hours and his daughter can dig the same size ditch in 4 hours... (answered by ewatrrr)
A man can dig a ditch in 3 hours and his daughter can dig the same size ditch in 5 hours. (answered by Alan3354)
One man can dig a canal in 60 days. How many days will 5 men take if they work at the... (answered by stanbon)
It takes 4 men working full time 42 days to do a job. If 1 guy only works half the time,... (answered by josgarithmetic)
17 men can dig a ditch 26m long in 18 days , working 8 hours a day . How many more men... (answered by josmiceli)
If it takes A 3 days to dig a ditch. B 6 days and C 12 days. How long will it take them... (answered by richwmiller)