SOLUTION: Sheila, Janice and Karen working together at the same rate can complete a job in 3 1/3 days. Working at the same rate, how much of the job could Janice and Karen do in one day?

Algebra.Com
Question 1034203: Sheila, Janice and Karen working together at the same rate can complete a job in 3 1/3 days. Working at the same rate, how much of the job could Janice and Karen do in one day?
Thanks; I'm familiar with the standard 1/t-1 + 1/t-2 = 1/x where the first two are the times of those individuals and x is their time working together, but I don't know how to adapt this formula to the problem I've written. If you have a reference for that problem, so I could review it further, I'd really appreciate it. Garrett

Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
Sheila, Janice and Karen working together at the same rate can complete a job in 3 1/3 days. Working at the same rate, how much of the job could Janice and Karen do in one day?
=====
Let rate for each of Sh, Ja, and Ka be 1/t
------
Together rate = 1/(3 1/3) = 1/(10/3) = 3/10
--------
3(1/t) = 3/10
1/t = 1/10
-----
t = 10 days (time each would take to do the job alone)
-----
Ja and Ka rate = (2(1/10) = 1/5 job/day
Cheers,
Stan H.
------------
-----

RELATED QUESTIONS

If 3 people working together at the same rate can do a job in 5 1/3 days, what fraction... (answered by ewatrrr)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
If 10 workers plant out a garden in 3 days, 6 workers will complete the same planting... (answered by josgarithmetic)
if x men working together at the same rate can complete a job in h hours, what part of... (answered by stanbon)
5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the... (answered by josmiceli)
Machine A working alone can complete a job in 3 1/2 hours. Machine B working alone can do (answered by ikleyn,MathTherapy)
A roofer and an apprentice are roofing a newly constructed house. In one day, the roofer... (answered by Boreal)
If 20 men can complete a piece of job in 8days, how long will it take 10 men to finish... (answered by Theo)
I have no idea how to even begin to solve this problem. "It takes Kay 8 days to... (answered by josgarithmetic)