SOLUTION: Hi, I need to do problem on linear programming and answer all those questions bellow the problem. This is a problem: A manufacturer produces

Algebra.Com
Question 23072: Hi, I need to do problem on linear programming and answer all those questions bellow the problem. This is a problem: A manufacturer produces two kinds of radios.
Model X takes 4 hours to produce, cost $8 in production, and sells for $15
Model Y takes 3 hours to produce, cost $7 in production, and sells for $12
If manufacture allots a total of 58 hours and $126 per week to produce radios, find his maximum income. How many of each model will produce this maximum profit?

X stands for: I think x stand for number model X radios will produces

Y stands for: I think y number model Y radios will produces
Constraint Equations:
8x+ 7y
15x+12y
I think if I know how to create equation then I will be able to to graphs
Objective Function:
Corner Coordinates:
Work shown in checking Coordinates:
Correct answer in a sentence
Graph

Answer by stanbon!(97)   (Show Source): You can put this solution on YOUR website!
Regarding your constraint equations:
8x+7y is a production cost expression. The equation
you want is 8x+7y<=126
You also need a production time eqation:
4x + 3y <= 58
Also x>=0 and y>=0
The Objective Function is an Income statement:
Income or I = 15x + 12y
Procedure:
Graph the four constraint lines on a single pair of xy axes.
The lines will form a triangle with two intersections on the
y-axis and one where the production-cost and the production-
time lines intersect.
Find the three points of intersection.
Put the (x,y) values into the objective function to determine
under what production conditions you maximize your income and
therefore your maximize profit.

RELATED QUESTIONS

Hi, im Very confused on Linear Graphs anything to do with it. First here is a problem... (answered by checkley71,allamericangirl)
I really would like someone to show me how to graph this problem: {y < = -x+6 x-2y > = (answered by solver91311)
Please help me solve this problem: If 18 men take 10 hours to build a wall, how manu... (answered by solver91311,josgarithmetic)
I have to graph points on a graph with this linear programming problem: 16X-13Y=79 I... (answered by rfer)
how do you solve a linear programming... (answered by Edwin McCravy)
here is linear programming question I am having trouble with. Can you show me how to... (answered by Fombitz)
I need help solving this word problem we are to use a system of linear equations to solve (answered by richwmiller)
Hi, Need some help on this question. It's a practice test question and I'm a bit... (answered by solver91311)
Hi i need to show steps on how to do this problem and the problem is 4x^2-3x+10=4. Can... (answered by lynnlo)