1. Algebra solution
Let R be rate of work of the team B. (= the part of job the team B complete dayli).
Then the rate of work of the team A is twice of it, i.e. 2R
From the condition, we have
2R + R = <<<---=== it is exactly what the condition says about two reams A and B working together.
This equation is 3R = , or, equivalently, R = = , which exactly means that the team B will complete the job in 18 days.
Then you may conclude that the team A will complete the job in 18/2 = 9 days.
Solved.
2. Logic solution
Team A works as two teams B.
Since A + B complete the job in 6 days, it means that three teams B working together will complete the job in 6 days.
Hence, one single team B will complete the job in 3*6 = 18 days working alone.
Then the Team A will complete it in 9 days working alone.
Check. + = = = . ! Correct !
Solved mentally, without using equations.
------------------------
It is a standard and typical joint work problem.
There is a wide variety of similar solved joint-work problems with detailed explanations in this site. See the lessons
- Using Fractions to solve word problems on joint work
- Solving more complicated word problems on joint work
- Selected joint-work word problems from the archive
Read them and get be trained in solving joint-work problems.
Also, you have this free of charge online textbook in ALGEBRA-I in this site
- ALGEBRA-I - YOUR ONLINE TEXTBOOK.
The referred lessons are the part of this textbook under the topic
"Rate of work and joint work problems" of the section "Word problems".
Save the link to this online textbook together with its description
Free of charge online textbook in ALGEBRA-I
https://www.algebra.com/algebra/homework/quadratic/lessons/ALGEBRA-I-YOUR-ONLINE-TEXTBOOK.lesson
to your archive and use it when it is needed.