SOLUTION: If it takes 3 workers 15 days to complete a job, how long would it take 5 workers to complete the same job?

Algebra.Com
Question 1006018: If it takes 3 workers 15 days to complete a job, how long would it
take 5 workers to complete the same job?

Answer by AnlytcPhil(1806)   (Show Source): You can put this solution on YOUR website!
If it takes 3 workers 15 days to complete a job, how long
would it take 5 workers to complete the same job?
The least common multiple of 3 and 5 workers is 15 workers.

it takes 3 workers 15 days to complete a job
Therefore it would take 15 workers (5 times as many workers)
only 1/5th of 15 days or 3 days to complete a job.

Therefore it would take 5 workers (only 1/3 as many workers)
3 times 3 days or 9 days to complete a job.

Edwin

RELATED QUESTIONS

If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)
If 15 workers can complete a job in 20 days, how long should it take 25 workers to... (answered by ankor@dixie-net.com)
If it takes workers A and B 2 days to complete a job. And it takes workers B and C 3 days (answered by ankor@dixie-net.com)
If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to... (answered by addingup)
how long will it take 8 workers to complete a job that took 5 workers to complete in 10... (answered by richwmiller)
Working together, 4 skilled workers can complete a job in 5 days. However, 5 semi-skilled (answered by ankor@dixie-net.com)
if it takes 9 men 15 days to complete a construction job, how long would it take to... (answered by ankor@dixie-net.com)
It takes 20 workers a total of 30 days to pave a highway. How many days would it take 15... (answered by josgarithmetic,askhari139)
Ten workers could do the job in 12 days. If 8 workers worked for 5 days and then half of... (answered by ankor@dixie-net.com)