Question 449416: Each of two road graders can pave a certain section of the road in 15 hours working alone. After two machines have been working for 2 hours they are joined by an older model that would take 20 hours to pave the section road by itself. How long after the first two machines began working will it take the three machines to pave the section of the road?
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
Each of two road graders can pave a certain section of the road in 15 hours working alone. After two machines have been working for 2 hours they are joined by an older model that would take 20 hours to pave the section road by itself. How long after the first two machines began working will it take the three machines to pave the section of the road?
------------------------
Rate of each road grader = 1/15 job/hr
-----
Rate for 2 of the road graders working together = 2/15 job/hr
---------------------------
Older model rate = 1/20 job/hr
--------------------------------------
How long after the first two machines began working for 2 hrs will it take the three machines to pave the section of the road?
---
Let the # of hrs required be "x":
2(2/15) + x(1/15 + 1/15 + 1/20) = 1 job
-------
(4/15) + x[(4 + 4 + 3)/60] = 1
---
(11/60)x = 11/15
x = 4 hrs. (Additional time needed to finish the job)
===================================
Cheers,
Stan H.
============

RELATED QUESTIONS

Each of two road graders can smooth a section of road in 10 hours working alone. After... (answered by mananth)
A road crew can pave 1.5 miles of road in an eight hour shift. If they were stopped after (answered by jojo14344)
One road crew can pave a section of highway in 15 h. A second crew can do the same job in (answered by josgarithmetic,ikleyn,Alan3354,greenestamps)
Working alone two metal crushers can each process one truckload of aluminum cans in 25... (answered by scott8148)
a new machine that deposits cement for a road requires 12 hours to complete one-half mile (answered by josgarithmetic)
Two road crews, working together, repaired 1 mile of road in 4 hours. Working separately, (answered by checkley71)
two roads crew working together repaired 1 mile of the road in four hours. working... (answered by ankor@dixie-net.com)
three old machines together required 80 min to do a certain job. two new machines were... (answered by ankor@dixie-net.com)
It takes nine days for 8 worker to pave a stretch of road. If each worker works at the... (answered by Mathtut)