A contractor undertook to build a road in 200 days he employed 140 men after 60 days he found that only one fourth of the road could be built
how many additional Men should be employed to complete the work in time
The 140 men, in the 60 days, worked at a rate of 33,600 "man-days"
With ¼ of job completed, ¾ remains to be completed in 140 (200 – 60) days
At the same rate (33,600 "man-days"), and with number of additional men being A, we get:
_____________
140 + A = 60(3)
A, or additional number of men needed to complete job =
Joscemeli, you're WAY, WAY off!!
Based on your answer, and with that number of additional men, for a total of 740,
it sounds more like building a skyscraper, a toll-bridge, or the railroad, I guess!