SOLUTION: A contractor who does not meet the deadline on the construction of a building is fined $40,000 per day for each of the first ten days of extra time, and for each additional day the

Algebra.Com
Question 1119632: A contractor who does not meet the deadline on the construction of a building is fined $40,000 per day for each of the first ten days of extra time, and for each additional day thereafter the fine is increased by $8,000. If the contractor is fined $1,008,000, by how many extra days was the construction delayed?
Answer by josgarithmetic(39623)   (Show Source): You can put this solution on YOUR website!
-------------------------------------------------------------------
A contractor who does not meet the deadline on the construction of a building is fined $40,000 per day for each of the first ten days of extra time, and for each additional day thereafter the fine is increased by $8,000. If the contractor is fined $1,008,000, by how many extra days was the construction delayed?
------------------------------------------------------------------



-
The increase after first ten days is ambiguous. Could be a sequence.
ADDITIONAL DAYS       FINE
1                     48000
2                     54000
3                     62000
4                     70000
5                     78000
6                     86000     ------398000
7                     94000
8                    102000     -------594000
9                    110000



The extra days, some unknown n, which lead up to fines of 608000 dollars.

Sum from 48000 to 8000(n-1) is $608000.

------summation formula;
Algebra steps lead to ,...
...


-



The solution looks like days extra after the first ten.

RELATED QUESTIONS

A project must be finished in 80 days. Contractor A costs $ 150 a day; Contractor B costs (answered by ewatrrr)
Juan’s boss has asked him to enter data for at least 60 spreadsheets. He has given him a... (answered by stanbon)
If 1200 persons can finish the construction of a building in 40 days, how many persons... (answered by richwmiller)
A Master contractor and his apprentice could spackle the interior walls of a new home in... (answered by ankor@dixie-net.com)
A retail shopping centre is in the market for $ 30 000 000. the following information is... (answered by ikleyn)
A retail shopping centre is in the market for $ 30 000 000. the following information is... (answered by ikleyn)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
A building contractor is to dig a foundation 40 feet long, 30 feet wide, and 14 feet... (answered by macston)