Question 993577: a man paint a house in 4 days and his son paint the house in 6 days. how many days will both take to paint the house if they work together ?
Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39617) (Show Source): You can put this solution on YOUR website!
d, how many days if both work together
Rates are additive for agents together, and rate should be arranged in unit .
Answer by ikleyn(52781) (Show Source): You can put this solution on YOUR website!
.
For similar and many other "joint work" problems see the lesson Using fractions to solve word problems on joint work in this site.
It is free of charge and without registration.
RELATED QUESTIONS
a man paint a house in 2 days while his son paint the same house in 4 days. how many days (answered by vleith)
I man can paint a house in 6 days and his son in 12 days. How many days will it take them (answered by ankor@dixie-net.com)
Jean paints a house in 4 days. Brett can paint the same house in 6 days and Joe can paint (answered by rwm)
Tyrin can paint a house in 4 days. Tahjai can paint the same house in 5 days. How many... (answered by bonster)
A man can paint a certain house in 5 days. He and his brother can do the job together in... (answered by josgarithmetic,ikleyn)
42. Tyrin can paint a house in 4 days. Tahjai can paint the same house in 5 days. How... (answered by vertciel)
If 4 painters can paint a house in 9 days,how many days would it take 6 painters to paint (answered by amoresroy)
It takes a contractor 4 days to paint a house. His apprentice takes 6 days to paint the
(answered by richwmiller)
A can paint a certain house in 10 days and B can paint the same house in 12 days. How... (answered by Alan3354)