So my question is : If a carpenter can roof a house in 10 days and another can do the same roof in 14 days, how many days will it take if they work together?
I would like you to tell me where I went wrong.
Here is the equation that I came up with.
1/10 + 1/14 = 1/t
I know I am missing something because I keep having issues with these types of problems.
Thanks,
Anthony
That equation is correct!! Good job!
This is what you have:
7t + 5t = 70 -------- Multiplying by CD, 70t
12t = 70
t, or time = , or days