Question 991499: A paint job can be done by 10 men in 6 hours or by 18 boys in 4 hours. If only five men and 8 boys are available and all work together how long would it take them to do the job?
Answer by josgarithmetic(39799)   (Show Source): You can put this solution on YOUR website!
R, rate for one man
r, rate for one boy
t, the unknown time if the described group works together

;
Most important is that this system makes sense. If it does, then you you what to do.

RELATED QUESTIONS

A paint job can be done by 10 men in 6 hours or by 18 boys in 4 hours. If only 5 men and... (answered by ankor@dixie-net.com)
If 6 men can harvest a field in 60 working hours, and a man works three times as fast as... (answered by Theo)
4 men and 10 boys can solve a task in 18 days . how many days will require to solve the... (answered by edjones)
Q1. if 2 men or 3 women or 6boys can do a piece o work in 70 days,in what time would 2... (answered by ankor@dixie-net.com,vvnrichards)
Three men can individually do a job in 5, 6 and 7 hours respectively. What is the... (answered by Edwin McCravy)
20 men or 30 boys can do a certain job in 20 days. how long will it take 6 men and 15... (answered by ankor@dixie-net.com)
A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10... (answered by ikleyn,Edwin McCravy)
If 4 men or 7 boys can do a work in 29 days, then 12 men and 8 boys will do the same work (answered by ankor@dixie-net.com)
If 6 men and 8 boys can complete a piece of work in 10 days and 8 men and 6 boys can... (answered by ikleyn)