SOLUTION: if father done a job in 12 days and son done in 6 days?how many days they takes together to done this job?
Algebra.Com
Question 987364: if father done a job in 12 days and son done in 6 days?how many days they takes together to done this job?
Answer by Boreal(15235) (Show Source): You can put this solution on YOUR website!
In one day, father does (1/12) and son does (1/6)
Together, they do (3/12) of the job in 1 day.
1/(3/12)=4 days to do the job together.
RELATED QUESTIONS
if 10 persos done a job in 18 days then 12 persons done the same job in how many... (answered by josgarithmetic)
Two workmen have to finish a job. If they work together the job will be done in 12 days.... (answered by josgarithmetic)
mr a can do a job for 3 days while mr b can do the same job for 6 days. if the two of... (answered by stanbon)
it takes doug 6 days to roof a house. if his son helps him,the job can be done in 4 days. (answered by chitra,Edwin McCravy)
A can finish a certain job in 10 days if B will help for 6 days. The same work can be... (answered by ankor@dixie-net.com)
a,b, andc can finish a job in 6 days. if b and c work together, the job will take 9... (answered by ankor@dixie-net.com)
A and B do a job in 12 days . A did for 8 days then rest job was done by B in 20 days.... (answered by stanbon,filmi101)
A painter works on a job for 10 days and then is joined by a helper. Together they... (answered by ankor@dixie-net.com)
A painter works on a job for 10 days and is then joined by her helper. Together they... (answered by ankor@dixie-net.com)