SOLUTION: Workman A's rate of doing work is twice that of Workman B's. One day, A & B work together for 8 hrs, then B due to injury stops and A finishes the rest of the job in 2 hrs. How lon

Algebra.Com
Question 984471: Workman A's rate of doing work is twice that of Workman B's. One day, A & B work together for 8 hrs, then B due to injury stops and A finishes the rest of the job in 2 hrs. How long would it take B to complete the job alone?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Workman A's rate of doing work is twice that of Workman B's.
One day, A & B work together for 8 hrs, then B due to injury stops and A finishes the rest of the job in 2 hrs.
How long would it take B to complete the job alone?
:
let a = time required by A to do the job
He works twice a fast as B, therefore
let 2a = time required by B to do the same job
let the completed job = 1
:
A works a total of 10 hrs, B works 8 hrs
The shared work equation
+ = 1
Multiply equation by 2a, cancel the denominators and you have:
2(10) + 8 = 2a
20 + 8 = 2a
28 = 2a
a = 14 for A to do the job alone
then
2(14) = 28 hrs for B to do the job alone
:
;
See if that works out using decimals
+ = 1
.7143 + .2857 = 1

RELATED QUESTIONS

Workman A's rate of doing work is twice that of Workman B's. One day, A & B work... (answered by josmiceli)
The workman A finishes the job 2 hours faster than the workman C, and 1 hour slower than... (answered by josgarithmetic,josmiceli)
Two workmen have to finish a job. If they work together the job will be done in 12 days.... (answered by josgarithmetic)
Hi, I am having difficulty putting this problem into an equation even though I know the... (answered by ankor@dixie-net.com,scott8148)
If A's rate of doing work is to B's is 6:8 and A does a piece of work in 50 days, how... (answered by rwm,wilmarugsad)
1. find three consecutive even integers whose sum is 42. 2. the difference of the... (answered by ankor@dixie-net.com)
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less (answered by richwmiller)
A and B are the work of a full 8 days. After 6 days, the two work together, 'A' work... (answered by Theo)
) An employee is working 6 days a week from Monday to Saturday. Assume the overtime for... (answered by josgarithmetic)