SOLUTION: 12 men can complete a work in ten days. 20 women can complete the same work in twelve days. 8 men and 4 women started working and after nine days 10 more women joined them. How ma

Algebra.Com
Question 983773: 12 men can complete a work in ten days. 20 women can complete the same work in twelve days. 8 men
and 4 women started working and after nine days 10 more women joined them. How many days will they
now take to complete the remaining work?

Found 3 solutions by solver91311, josgarithmetic, MathTherapy:
Answer by solver91311(24713)   (Show Source): You can put this solution on YOUR website!


If 12 men can do a job in 10 days, then 12 men can do of the job in 1 day, and then 1 man can do of the job in 1 day. Similarly, 1 woman can do of the job in 1 day.

So 8 men and 4 women working for 9 days do of the job, leaving of the job for 8 men and 14 women to accomplish in days, so:



Solve for

John

My calculator said it, I believe it, that settles it

Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
R rate of 1 man
r rate of 1 woman

-


Let t be the time needed to complete after some of the job was done using the described combination of men and women.


Simplify this and solve for t.





LCD is 120.
Multiply LCD by both sides.




, this many days.

Answer by MathTherapy(10552)   (Show Source): You can put this solution on YOUR website!

12 men can complete a work in ten days. 20 women can complete the same work in twelve days. 8 men
and 4 women started working and after nine days 10 more women joined them. How many days will they
now take to complete the remaining work?
Time taken by 8 men and 14 women to do remaining  of work:  days 

RELATED QUESTIONS

3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to... (answered by josmiceli)
if 8 men or 12 women can complete a work in 25 days than 6 men and 11 women will complete (answered by richwmiller)
24 men can complete a work in 16 days.32 women can complete the same work in 24 days.16... (answered by josgarithmetic)
4 men & 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in (answered by josgarithmetic)
8 men and 16 women can do a work in 8 days.40 men and 48 women can do the same work in 2... (answered by josgarithmetic,MathTherapy)
4 men and 6 women can complete a work in 8 days while 3 and 7 women can complete it in 10 (answered by ankor@dixie-net.com)
10 men and 15 women complete a job in 6 days, 1 man can complete the same work in 100... (answered by josmiceli)
2 men and 3 women can do a piece of work in 16 days .In how days can 4 men and 6 women do (answered by richwmiller)
12 men alone can complete a piece of work in six days, whereas 10 men and 21 women take... (answered by stanbon)