SOLUTION: a job is expected to take 8 days if 6 persons are employed. how long would it continue if 2 more persons are engaged.
Algebra.Com
Question 981524: a job is expected to take 8 days if 6 persons are employed. how long would it continue if 2 more persons are engaged.
Answer by josgarithmetic(39617) (Show Source): You can put this solution on YOUR website!
RT=J uniform rates for doing a JOB.
, two equations.
RELATED QUESTIONS
A job is expected to take 8 days if 6 person are employed.
How long would it... (answered by macston,josgarithmetic)
15 persons can do the job in 6 days, how many extra persons are required if it would have (answered by nyc_function)
6 persons worked 8 days to finish 3/5 of a building,. If 2 more persons join them , how... (answered by josgarithmetic)
A contractor engaged 30 persons to construct the road in 30 days but only one fourth of... (answered by jorel555)
It takes 2 persons 3 hours to complete a job, if you add a third person to the job next... (answered by ewatrrr)
The amount A paid to a work crew varies jointly as the number of persons working N and... (answered by josmiceli)
1. Kristen could shovel a large parking lot after a 12" snowfall in 5 hours. It would... (answered by 303795)
A 3-men crew can do a certain job in 3 weeks and 2 days, if we are to hire 4 men crew... (answered by josmiceli)
If the food in the basket is sufficient to feed 10 persons in 12 days, how many days... (answered by josgarithmetic)