SOLUTION: A,B can do a piece of work 6,8 hours respectively.If they work for a day alternatively.Suppose A beginning the work,in how many days work will be completed? i think answer is 6 ³/

Algebra.Com
Question 979565: A,B can do a piece of work 6,8 hours respectively.If they work for a day alternatively.Suppose A beginning the work,in how many days work will be completed?
i think answer is 6 ³/2.
please explain this question.

Answer by josgarithmetic(39618)   (Show Source): You can put this solution on YOUR website!
Your description might be better understood as, "A and B working independently and not at the same time on the same job, take 6 and 8 hours respectively". They can still work "ALTERNATELY" on a task.

WORKER________RATE, job/hours
A_____________1/6
B_____________1/8

Now, the rest of the description gives A and B working in alternation. Each is working on the job separately, not simultaneously. We could try making calculation at a very low level.

(1/6)*1+(1/8)*1+(1/6)*1+(1/8)*1+....=1

Try maybe using a variable for the number of day that EACH may possibly work alone, although the true result could be non-whole.
Say like, A and B each works x days.




, which is days.

Try to now go back to the lowest day to day level.
First let A work for 3 days and B work for 3 days, knowing that A and B never work on the same day.





-
This way, three days for A and three days for B, done in alternation,
completes only of the job, and the work began with worker A. B worked last, so A does ONE MORE day...
-




This then is slightly MORE THAN 1 JOB.

Let me just summarize as much as to say, A will work for 4 days, and then B will have worked 3 days, plus most of the last day but not all of it.

RELATED QUESTIONS

A, B & C can do a piece of work in 30,20 & 10 days respectively. A is assisted by B on... (answered by ankor@dixie-net.com)
While working 7 hours day, A alone can complete a piece of work in 6 days and B alone in... (answered by solver91311)
Kong can do a piece of work in 8 hours, (answered by richwmiller)
A can do a piece of work in 10 days. If A and B work together they can finish it in 6... (answered by Narsinghchauhan8960103366)
A can do a work in 8 days and B can do a work in 7 days. A works on the first day ,B... (answered by ankor@dixie-net.com)
Ramesh , Suresh and Harish can do a piece of work in 15 days, 10 days and 6 days... (answered by mananth)
If a woman works for 3 1/2 hours per day, she can finish a piece of work in 10 days. How... (answered by Theo)
If M,K,L can do a work in 4, 6 , and 8 hours; if they work simultaneously then what... (answered by josmiceli)
A, B, & C can do a piece of work in 10, 9, 15 days respectively. They started the work... (answered by richwmiller)