Question 979061: 24 men can plough 42 hectares of land in 14 days . How many days will it take 16 men to plough 64 hectares
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
r, rate for one man
t, unknown days count for question part


RELATED QUESTIONS

If 24 men can plough 42 hectares of land in 14 days.how many days will it take 16 men to... (answered by ewatrrr)
harshi.talesara@gmail.com 10 bulls can plough 13 hectares of farmland in 7 days. How... (answered by ikleyn)
15 men were hired to plough 100 acres of land in 14 days.How many more men will be... (answered by josgarithmetic,MathTherapy,ikleyn)
A farmer can plough 38 ares in a day. His field measures 3.01 hectares, but he wants to... (answered by ankor@dixie-net.com)
15 men plough a land in 14 days working 12 hours daily.How many days will be taken by 21... (answered by josgarithmetic)
4 cows can plough 7 hectares of field in 3 days. how many hectare of field can be... (answered by stanbon)
If 8 men could plough a field in 9 days, how many days would it take 18 men working at... (answered by neatmath)
Dinu and Hemu can plough a field in 15 days. If Dinu alone can plough 1/8 of the field in (answered by ptaylor)
Dinu & Hemu can plough a field in 15 days . If Dinu alone can plough 1/8 of the field in... (answered by josgarithmetic,ikleyn)