SOLUTION: A contractor undertakes to build a bridge 12 km long in 350 days and employs 45 men. At the end of 200 days he finds that 41/2 km of the bridge have been completed. How many additi

Algebra.Com
Question 973750: A contractor undertakes to build a bridge 12 km long in 350 days and employs 45 men. At the end of 200 days he finds that 41/2 km of the bridge have been completed. How many additional men must he now employ in order to get the work finished in time? (I need solution with a proper explanation)

Found 2 solutions by josgarithmetic, MathTherapy:
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
RT=J rate time job.

Let r be work rate for one worker or man.
Let n be the number of additional men needed for the remaining expected days.


The first rate equation was an expectation or estimate which fell short of the 12 km length of the job. This equation gives the one-man work rate in kilometers per day. This value for r will be used in the second equation for finding the number of additional n men required for completing the remaining length of bridge, twelve minus four and a half kilometers of bridge, in the required or earlier estimated 350 days. Since 200 days were used and the bridge not yet finished, the contractor wants to be able to finish the unbuilt bridge within 150 days after the first 200 days.

Examine the system's equations carefully to understand that they are in the uniform rates form, RT=J.

Answer by MathTherapy(10552)   (Show Source): You can put this solution on YOUR website!

A contractor undertakes to build a bridge 12 km long in 350 days and employs 45 men. At the end of 200 days he finds that 41/2 km of the bridge have been completed. How many additional men must he now employ in order to get the work finished in time? (I need solution with a proper explanation)
An additional  men will be needed. 

RELATED QUESTIONS

An engineer undertakes a project to build a road of 15 km long in 300 days and employs 45 (answered by richwmiller,Theo)
A contructor undertakes to build a wall 1000 meter long in 50 days. He employed 56 men... (answered by stanbon,ankor@dixie-net.com,MathTherapy)
A man undertakes to do a piece of work in 150 days. He employs 200 men. He finds that... (answered by richwmiller)
A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men.... (answered by macston)
A road contractor wanted to build a 200 meter long road in 30 days and employed 20... (answered by ankor@dixie-net.com,MathTherapy)
a contractor decides that he can build a barn in 8 weeks using 5 men. if he employs 3... (answered by Fombitz,ewatrrr)
a contractor engages 24 workers to build a road in 30 days. after 24 days he finds... (answered by TimothyLamb)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)