SOLUTION: Greg and Joan are taking a job that is scheduled to take them 8 days to complete. Their friend Brenda decides she would join them in the job. Assuming the friends all work at the s

Algebra.Com
Question 972351: Greg and Joan are taking a job that is scheduled to take them 8 days to complete. Their friend Brenda decides she would join them in the job. Assuming the friends all work at the same rate, how much time will the job take all three friends to complete?
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
Greg and Joan are taking a job that is scheduled to take them 8 days to complete. Their friend Brenda decides she would join them in the job. Assuming the friends all work at the same rate, how much time will the job take all three friends to complete?
-------
Let the rate for each of the three be "r".
------
Equation::
rate + rate = 1/8 job/day
2r = 1/8
r = 1/16 job/day (rate for each person)
-------
Equation:
3r = 3/16 job/day ((rate when all three are working together)
----
Ans:: (16/3) days/job = 5 1/3 days for the three of them to do the job together.
=========================
Cheers,
Stan H.

RELATED QUESTIONS

Greg and Joan are trying to decide whether to take on a job that is scheduled to take... (answered by josgarithmetic)
Greg and Joan are trying to decide whether to take on a job that is scheduled to take... (answered by josmiceli,Boreal,MathTherapy)
Brenda the Brave sets off to climb a mountain which is 12,000 feet high. She plans to... (answered by stanbon,butofcourseric)
climb a mountain which is 12,000 feet high. She plans to climb 3000 feet each day, before (answered by JenniferTutors)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
Greg and Randy together can repair a car in 4 4/17 hours. Randy, working alone could do... (answered by josgarithmetic)
You have 8 machines that take six days to complete a job , how many machines does it take (answered by stanbon)
an electrical contractor is planning to complete a lighting job by useing two separate... (answered by richwmiller)
If it takes 8 men to complete a job in 8 days, how many days would it take 1... (answered by stanbon)