SOLUTION: 3 workers can do a job in 36 days. How long would it take 2 workers to finish the same job?

Algebra.Com
Question 971884: 3 workers can do a job in 36 days. How long would it take 2 workers to finish the same job?
Found 2 solutions by macston, Edwin McCravy:
Answer by macston(5194)   (Show Source): You can put this solution on YOUR website!
3 men x 36 days=108 man days
108 man days/2 men=54 days
ANSWER: It would take 2 men 54 days to do the job.

Answer by Edwin McCravy(20060)   (Show Source): You can put this solution on YOUR website!
3 workers can do a job in 36 days. How long would it take 2 workers to finish
the same job?

Here's an easier way, at least an easier way to REMEMBER how to do
ALL proportion problems, using common sense:

Common sense tells us that the answer is going to be MORE than 36 days,
because it takes less workers longer.

Take the two given quantities that CORRESPOND, namely 3 workers and 2 workers.

Put one over the other so that the fraction will be MORE than 1.
That fraction is 3/2 

            [it's not 2/3 because 2/3 would be LESS than 1].

So multiply 36 days by  and get 54 days.

[Note: In other proportional problems when common sense tells us that the answer will
be LESS than the other, we make the fraction of the given corresponding quantities
so that it will be LESS than 1.]

Edwin

RELATED QUESTIONS

If M workers can do a job in D days, how long would it take 40 workers to do the same... (answered by ptaylor)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
If it takes 3 workers 15 days to complete a job, how long would it take 5 workers to... (answered by AnlytcPhil)
Three workers can do a job in 12 days. Two of the workers work twice as fast as the... (answered by josgarithmetic)
If 15 workers can complete a job in 20 days, how long should it take 25 workers to... (answered by ankor@dixie-net.com)
4 skilled workers can do a job in 5 days, 5 semi-skilled workers can do the same job in 6 (answered by josgarithmetic)
A group of 3 workers need 20 days to do a certain job. How long would it take a group of (answered by josgarithmetic)
A group of 3 workers need 20 days to do a certain job. How long would it take a group of... (answered by josgarithmetic)
If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)