Question 971758: In a rate of work problem, how do you set it up if it is phrased differently, as in "Joe can do a job in 3 hours, and working together with Charlie they completed the job in 2 hours, how long would Charlie take to do the job working alone?" I'm used to the more typical format where you are given each of their rates and then have to find each person's individual rate.
Answer by Boreal(15235) (Show Source): You can put this solution on YOUR website!
Joe (1/3) of job in an hour + Charlie (1/x) in an hour = 1/2 (of job in an hour)
Multiply by 6x common denominator.
2x + 6= 3x
x=6
Charlier does (1/6) of job per hour working alone. It takes him 6 hours to do it.
RELATED QUESTIONS
Bill can mow a lawn in 1 1/2 hours with a riding lawn mower. Joe can mow it in 2 1/2... (answered by unlockmath)
It takes Joe x hours to do a job. What part of the job can he do in 1 hour?
Jane takes (answered by ankor@dixie-net.com)
If Harry can do a job in 2 days, and Sally can do the job in 4 days, and Henry can do... (answered by stanbon)
Andrei Toom's word problem from his article... (answered by scott8148)
You can do a job in 4 hours and a co-worker can do the same job in 8 hour. How long will... (answered by jorel1380)
It takes Joe 12 hours to paint a fence, but Bob can do the job in 9 hours. How long does (answered by nerdybill,ankor@dixie-net.com)
This is my second time using this section-the first response was really helpful, so... (answered by prince_abubu)
Joe can do a job in 12 days after he has worked for 4 days he is joined by Casey and it... (answered by scott8148)
Tom can do a job in 4 hours, Joy can do the same job in 3 hours, How many hours will it... (answered by josmiceli)