Question 970821: 10 men working 5 hrs per day can complete a pice of work in 12 days. How many men will be required to complete the same work in 15 days if they work for 3 hrs per day?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
10 men working 5 hrs per day can complete a piece of work in 12 days.
Find how many many hr required to do the job
10 * 5 * 12 = 600 man-hrs
:
How many men will be required to complete the same work in 15 days if they work for 3 hrs per day?
let m = no. of men required to accomplish this
3 * 15 * m = 600
45m = 600
m = 600/45
m = 13 ~ 14 men to do the same job working 3 hrs a day for 15 days

RELATED QUESTIONS

10 men working 3 hrs a day can complete a wall in 8 days. How many men will be required... (answered by josmiceli,richwmiller)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many... (answered by robertb,MathTherapy)
If 15 men complete a work in 20 days, then how many men will be required to do the same... (answered by josgarithmetic)
Working for 8 hrs daily, 40 men can complete in 21 days. Working for 10 hrs daily, If the (answered by ptaylor)
12 men can complete a work in 4 days. how many men will be required in order to complete... (answered by ankor@dixie-net.com)
10 men working for 6 days of 10 hours each finish 5/21 of a piece of work. How many men... (answered by richwmiller)
If a group of 24 men working 8 hrs a day can complete building a wall in 12 days then in (answered by ankor@dixie-net.com,DEEPAK K)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)