SOLUTION: 12 men can finish half a job in 35 minutes; how many more men are needed if the remaining job should be completed in 15 minutes?
Algebra.Com
Question 970659: 12 men can finish half a job in 35 minutes; how many more men are needed if the remaining job should be completed in 15 minutes?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
12 men can finish half a job in 35 minutes;
Find how many man-minutes to complete half the job
12 * 35 = 420 man minutes, to do half the job
:
how many more men are needed if the remaining job should be completed in 15 minutes?
Let m = no. of men to accomplish this
15m = 420
m = 420/15
m = 28 men required
RELATED QUESTIONS
Eight men can finish a painting job in 10 days. If the task needs to be completed 2 days... (answered by nshah11,hibiskus)
a piece of work can be done by 40 men in 48 days. after 15 days, 18 men were transferred... (answered by stanbon)
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
12 men can do a job in 8 days. If after 5 days,they are joined by 4 more men, how many... (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
5 men are hired to complete a job. If one more man is hired, the job can be completed 8... (answered by josgarithmetic,Edwin McCravy,Theo,AnlytcPhil,ikleyn,greenestamps,math_tutor2020)
5 men are hired to complete a job. If one more man is hired, the job can be completed... (answered by Edwin McCravy)
15 men complete a job in 10 days, 8 men finish same job ? how many... (answered by josgarithmetic)