Question 968964: if 6 men take 18 days to complete the hauling jobs how many days would be required to complete this task if three additional men were hired?
Answer by amarjeeth123(570)   (Show Source): You can put this solution on YOUR website!
6 men take 18 days to complete the hauling jobs
9 men will take 6*18/9=12 days to complete the job
Answer=12 days

RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
If it takes 6 men to complete a job in 12 days, how many men would it take to complete... (answered by richwmiller)
If it takes 64 men 15 days to complete a job, how many more men would be required to... (answered by Alan3354,richwmiller)
If 2 men and 3 women can complete a task in 8 days; and 4 men and 5 women can complete a... (answered by Edwin McCravy)
John can complete a task in 18 days while Peter can complete it in 12 days. How many days (answered by math_helper)
Hi I really need help with these questions please. Could someone show their solution too... (answered by richwmiller)
If three men take 3 days to complete a piece of work, how many days will 2 men take to... (answered by reynard2007)
If it takes 20 people to complete as task in 12 days. How many people will it take to... (answered by Edwin McCravy)