Question 965904: A crew will arrive in 1 week and begin filming a city for a movie. The mayor wants to clean the streets. 2 teams are available. Team 1 will take 200 hours to complete. Team 2 will take 500 hours to complete. How long will it take if both teams work together?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
Let = time in hours for both teams
working together to complete job
------------------
Add their rates of working to get their
rate working together:
[ 1 job ] / [ 200 hrs ] + [ 1 job ] / [ 500 hrs ] = [ 1 job ][ / [ t hrs ]
Multiply both sides by
Working together, it will take them
142.86 hrs to finish
--------------------
check:
error due to rounding off -OK
RELATED QUESTIONS
A crew will arrive in one week and begin filming a city for a movie. The mayor is... (answered by josgarithmetic,ikleyn,greenestamps)
A production company spent 59 1/2 days filming its first movie. The company's second... (answered by josgarithmetic)
The city of Waterville has received a grant for $950,000 to spend on various projects:... (answered by mananth)
The city of Waterville has received a grant for $950,000 to spend on various projects:... (answered by josmiceli)
This word problem is under a section of my homework called slove the equation.
The... (answered by ankor@dixie-net.com)
The clean-up crew of a medium-sized firm has an average clean-up time of 72.0 total hours (answered by Boreal)
I have finals coming up and I still don't understand much of Rational Expressions. Can... (answered by josgarithmetic,ankor@dixie-net.com)
If three people working together can clean an office suite in two hours, how long will it (answered by solver91311,bucky)
A town's old street sweeper can clean the streets in 60 hours. The old sweeper together... (answered by scott8148,mjackson73)