SOLUTION: A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left then B and C together completed the work in 10 mo
Algebra.Com
Question 962901: A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left then B and C together completed the work in 10 more days. A alone can complete the work in?
Answer by LinnW(1048) (Show Source): You can put this solution on YOUR website!
Set a = the rate of A in (piece of work)/day
b = the rate of B in (piece of work)/day
c = the rate of C in (piece of work)/day
Below is the equation for all three working together.
( 10 days ) * ( a + b + c ) = 1(piece of work)
Next we have the equation were all work together for 4 days,
then only B and C continue for 10 more days.
( 4 days) * ( a + b + c ) + (10 days)( b + c) = 1(piece of work)
Since each left hand side is equal to 1 piece of work,
we have
( 10 days ) * ( a + b + c ) =
( 4 days) * ( a + b + c ) + (10 days)( b + c)
and
10( a + b + c ) = 4( a + b + c ) + 10( b + c)
10a + 10b + 10c = 4a + 4b + 4c + 10b + 10c
combining terms
10a + 10b + 10c = 4a + 14b + 14c
Notice that we can rewrite the above as
10a + 10(b + c) = 4a + 14(b + c)
if we subtract 10(b + c) from each side
10a = 4a + 4(b + c)
subtract 4a from each side
6a = 4(b + c)
divide each side by 4
6a/4 = (b + c)
Recall
( 10 days ) * ( a + b + c ) = 1(piece of work) or
10(a + b + c) = 1
so
10a + 10(b + c) = 1
Now substitute 6a/4 for (b + c) and we have
10a + 10(6a/4) = 1
10a + 15a = 1
25a = 1
This means that A at rate a will take 25 days to complete the work.
RELATED QUESTIONS
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
A can complete a job in 9 days, B can do the same job in 10 days and C can do it in 15... (answered by richwmiller)
A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days.... (answered by ptaylor,Edwin Parker)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A (answered by htmentor)
A, B, & C can do a piece of work in 10, 9, 15 days respectively. They started the work... (answered by richwmiller)
7) A, B, & C can do a piece of work in 10, 9, 15 days respectively. They started the work (answered by richwmiller)
A can do a piece of work in 12 days and B can do a piece of work in 18 days. They started (answered by dkppathak)