SOLUTION: 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.
Algebra.Com
Question 956605: 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.
Answer by lwsshak3(11628) (Show Source): You can put this solution on YOUR website!
70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days.
***
man-days required to dig 15000 sq m field=5*70=350
man-days required to dig 22500 sq m field=225/150*5/25*350=105
men required=105/25=4.2
RELATED QUESTIONS
12 men complete the 2400 square meter ploughing work in 10 days. how many men are... (answered by Alan3354)
If 12 persons working 12 hours a day dig 12 meter of tunnel in 12 days. How many men are (answered by josmiceli)
25 men dig a canal in 21 days. In how many days will 15 men dig it?
(answered by macston)
If 12 men can dig a trench in 8 days how many men can dig it in 6... (answered by josgarithmetic,greenestamps)
7 men can dig a drain in 10 days. how many men would dig the same drain in 14 days
(answered by josgarithmetic,ikleyn,greenestamps)
Fifteen carpenters can complete building a house in 45 days . How many extra men will be... (answered by ankor@dixie-net.com)
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench (answered by Edwin McCravy)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
If 2 men and 3 women can complete a task in 8 days; and 4 men and 5 women can complete a... (answered by Edwin McCravy)