Question 948826: A and B can do a work in 12 days and 20 days.A works alone for 4 days and then B joins to help.in how many days will they finish the job?
ans- A in 1 day = 1/12
B in 1 day = 1/20
A alone works for 4 days
therefore in 4 days A'work = 4*1/20= 1/5
Remaining work 4/5
then B joins......
Answer by Fombitz(32388) (Show Source): You can put this solution on YOUR website!
You made a mistake.
A working for 4 days would be,
So that leaves to complete.
.
.
.
So then use the rate for A and B together.
So then,
RELATED QUESTIONS
Mary alone can finish a painting job in 12 days. Gary alone can do the same jon in 20... (answered by richwmiller)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)
A and B can do a peice of work in 8 days whih A alone can take 12 days, how many days... (answered by Alan3354,ikleyn)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A and B can do a work in 20 and 30 days respectively. A worked for few days and with the (answered by richwmiller,ankor@dixie-net.com)
A and B can do a work in 20 and 30 days. A worked for few days and with the help of... (answered by richwmiller)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)