Question 943904: 1 man took 10 days to build a wall, and 1 man took 20 days to build a wall. How much days would the two man take to build a wall together
Answer by macston(5194) (Show Source): You can put this solution on YOUR website!
First man built 1 wall in 10 days=1 wall/10 days=1/10 wall/day
Second man built 1 wall in 20 days=1 wall/20 days=1/20 wall/day
Together they build 1/10 wall/day +1/20 wall/day=(1/10)(2/2)wall/day + 1/20 wall/day=2/20 wall/day + 1/20 wall/day=3/20 wall/day
Together the men build 3/20 of the wall in 1 day.
To build the whole wall =6 and 2/3 days
ANSWER Together it takes the men 6 and 2/3 days to build the wall.
RELATED QUESTIONS
60 man can build a wall in 4o days.5 mens quits in every 10 days. how many days required... (answered by josgarithmetic,MathTherapy)
3 men take 4 days to build a wall. if one man worked on that same wall, how long would he (answered by richwmiller)
it takes 8 men to build a wall in 30 days. How long would it take 10 men to build the... (answered by JulietG)
2 men take 12 days to build a bridge, how many days does it take for 1 man?
(answered by macston)
If 5 ppls takes 10 days to build a wall then 15 ppls take how many days to build the same (answered by ramkikk66)
if 20 men can build a wall in 5 days how many men will be required to build the same wall (answered by Theo)
if 20 men can build a wall in 5 days how many men will be required to build the same... (answered by greenestamps,ikleyn)
a bricklayer can build a brick wall in 2 days. His apprentice needs 3 days to build the... (answered by ikleyn)
If , It took 8 mens 10 hours to build a wall how long will it take for a single man to do (answered by Theo)