SOLUTION: Worker A finishes the job in 10 hrs; Worker B finishes it in 12 hrs, and worker C finishes it jn 15 hrs. After worker A worked alone for 2 hrs, and then B worked alome for 4 hours,

Algebra.Com
Question 935751: Worker A finishes the job in 10 hrs; Worker B finishes it in 12 hrs, and worker C finishes it jn 15 hrs. After worker A worked alone for 2 hrs, and then B worked alome for 4 hours, how many hours will it take C alone to finish the remaining work?

Found 2 solutions by ptaylor, josmiceli:
Answer by ptaylor(2198)   (Show Source): You can put this solution on YOUR website!
Let x = amount of time it takes worker C alone to finish the job
Worker A works at the rate of 1/10 of the job per hour
Worker B rate is 1/12 of the job per hour
Worker C rate is 1/15 of the job per hour
In 2 hours, worker A finishes (1/10)*2=2/10 = 1/5 of the job
In 4 hours worker B finishes (1/12)*4=1/3 of the job
Together A and B have finished 1/5 + 1/3=3/15+5/15=8/15 of the job leaving 7/15 yet to be finished
So our equation to solve is:
(1/15)*x=7/15
x=7 hours
CK
(1/10)*2+(1/12)*4+(1/15)*7 should equal 1 job
Hope this helps---ptaylor

Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
What fraction of the job did A finish in hrs?
A's rate is: ( 1 job ) / ( 10 hrs )

-----------------------
That means there is of the job left to do
B's rate is ( 1 job ) / ( 12 hrs )
B's fraction of the fraction left to do is:

is the fraction now done
That means there is of the job left to do
---------------
C's rate is ( 1 job ) / ( 15 hrs )
C can do of the job in:
hrs to finish the work


RELATED QUESTIONS

Worker A and worker B, working together, can finish a job in 12 days. After 8 days worker (answered by josmiceli)
When working together worker A and worker B take 8 hours to complete a project.Today they (answered by ankor@dixie-net.com)
Worker A can finish the job in 5 hrs, Worker B in 6 hrs. If they split the work in half (answered by ikleyn,josgarithmetic,greenestamps)
Two workers, if they were working together could finish a job in 12 days. If one worker... (answered by josgarithmetic)
i have solved that if Worker A finishes a job in 8 days and worker B finishes it in 12... (answered by josmiceli)
A welder requires 25 hrs to do a job on his own. After a welder and apprentice work on... (answered by ankor@dixie-net.com)
Two workers working together finished a job in 12 hours. Later the first worker made one... (answered by KMST)
It takes one worker 5 hrs to do the same job that it takes another worker 3hrs to do.If... (answered by stanbon)
Workman A's rate of doing work is twice that of Workman B's. One day, A & B work together (answered by ankor@dixie-net.com)