SOLUTION: A piece of work can be done by 6 men & 5 women in 6 days or 3 men & 4 women in 10 days. It can be done by 9 men & 15 women in ?
Algebra.Com
Question 930275: A piece of work can be done by 6 men & 5 women in 6 days or 3 men & 4 women in 10 days. It can be done by 9 men & 15 women in ?
Answer by ptaylor(2198) (Show Source): You can put this solution on YOUR website!
OK--
Let t=amount of time it takes 9 men and 15 women to do the piece of work.
6 men and 5 women work at the rate of 1/6 of the piece of work per day
3 men and 4 women work at the rate of 1/10 of the piece of work per day
Let x=amount of time it takes a man working alone to do the piece of work
Then the man works at the rate of 1/x of the piece of work per day
Let y= amount of time it take a woman working alone to do the piece of work
Then the woman works at the rate of 1/y of the piece of work per day
soooo our equations to solve are:
6/x + 5/y=1/6----eq1
3/x + 4/y=1/10----eq2
Multiply eq2 by 2
6/x + 8/y=1/5 and subtract eq1
3/y=1/5-1/6=6/30 - 5/30=1/30
3/y=1/30;
y=90 days ---time it takes 1 woman to do the piece of work
substitute into eq1
6/x + 5/90= 1/6
6/x + 1/18=1/6 multiply by 18x
108+x=3x
2x=108
x=54 days ----time it takes 1 man to do the piece of work
(9/54 + 15/90)t=1 (1 piece of work, that is)
(3/18 +3/18)t=1
t/3=1
t=3 days
CK
In 3 days, 9 men do (9/54)*3=26/54 = 1/2 of the piece of work
In 3 days, 15 women do (15/90)*3=1/2 of the piece of work
Hope this helps---ptaylor
RELATED QUESTIONS
A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10... (answered by ikleyn,Edwin McCravy)
10 men and 15 women can do a piece of work in 30 days, Calculate in how many days can the (answered by richwmiller,Alan3354)
A particular work can be completed by 6 men and 6 women in 24 days. Whereas the same work (answered by josgarithmetic)
Q1. if 2 men or 3 women or 6boys can do a piece o work in 70 days,in what time would 2... (answered by ankor@dixie-net.com,vvnrichards)
2 men and 3 women can do a piece of work in 16 days .In how days can 4 men and 6 women do (answered by richwmiller)
If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
4 men & 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in (answered by josgarithmetic)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
3 men and 5 women do a piece of work in 9 days and 2 men and 7 children do the same in 6... (answered by ankor@dixie-net.com)