SOLUTION: If 3 workers take 8 days to complete a job how many workers would be needed to finish the job in only 6 days if each worked at the same rate?
Algebra.Com
Question 928939: If 3 workers take 8 days to complete a job how many workers would be needed to finish the job in only 6 days if each worked at the same rate?
Answer by ewatrrr(24785) (Show Source): You can put this solution on YOUR website!
24/6 = 4 workers needed
RELATED QUESTIONS
If a certain job can be finished by 18 workers in 26 days. How many workers are needed to (answered by robertb)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
If it takes 3 workers 15 days to complete a job, how long would it
take 5 workers to... (answered by AnlytcPhil)
Hi
5 workers complete a job in 6 days. After 2 days, 3 workers left.
how many more days (answered by Theo)
Six workers can paint 4 houses in 8 days. How many additional workers are needed if the... (answered by edjones)
If a job can be completed by 2 workers in 10 days, then what is the number of workers... (answered by stanbon)
If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)
Five workers have been hired to complete a job. If one additional worker is hired, they... (answered by ikleyn,math_tutor2020)
3 workers can do a job in 36 days. How long would it take 2 workers to finish the same... (answered by macston,Edwin McCravy)