SOLUTION: A and B do a job in 12 days . A did for 8 days then rest job was done by B in 20 days. Find individually A and B can do in how many days.
Algebra.Com
Question 925250: A and B do a job in 12 days . A did for 8 days then rest job was done by B in 20 days. Find individually A and B can do in how many days.
Found 2 solutions by stanbon, filmi101:
Answer by stanbon(75887) (Show Source): You can put this solution on YOUR website!
A and B do a job in 12 days . A did for 8 days then rest job was done by B in 20 days. Find individually A and B can do in how many days.
---
Together rate:: 1/12 job/day
A's rate:: 1/a job/day
B's rate:: 1/b job/day
-----
Equations:
1/a + 1/b = 1/12
3(1/a) + 20(1/b) = 1
----------
Modify::
12b + 12a = ab
3b + 20a = ab
-----
Modify for elimination::
12b + 12a = ab
12b + 80a = 4ab
----
Subtract::
68a = 2ab
b = 34 days (time for B to do the job alone)
---
Solve for "a":
1/a + 1/34 = 1/12
1/a = 1/12 - 1/34
1/a = (34-12)/(12*34)
1/a = 22/(12*34)
a = (12*34)/22
a = 8.55 days (time for A to do the job alone)
----------------------
Answer by filmi101(1) (Show Source): You can put this solution on YOUR website!
1/a + 1/b = 1/12
8/a+ 20/b = 1
or we can write the equation as
12a+12b = ab
8a+ 20b = an
solving the equation we get a= 36 b= 18
RELATED QUESTIONS
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
a,b, andc can finish a job in 6 days. if b and c work together, the job will take 9... (answered by ankor@dixie-net.com)
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by stanbon)
mr a can do a job for 3 days while mr b can do the same job for 6 days. if the two of... (answered by stanbon)
Q1. if 2 men or 3 women or 6boys can do a piece o work in 70 days,in what time would 2... (answered by ankor@dixie-net.com,vvnrichards)
A,B, and C can finish a job in 6 days. If B and C work together, the job will take 9... (answered by edjones)
A can do a job in 6 days while B can do a job in 8 days. They worked together for 2 days... (answered by richwmiller)
A and B can do a work in 12 days and 20 days.A works alone for 4 days and then B joins to (answered by Fombitz)