SOLUTION: if it takes 8 1/2 hours for 6 workers to pave 140 meters of road how many hours would it take 4 works to pave 280 meters of road?
Algebra.Com
Question 922806: if it takes 8 1/2 hours for 6 workers to pave 140 meters of road how many hours would it take 4 works to pave 280 meters of road?
Answer by ptaylor(2198) (Show Source): You can put this solution on YOUR website!
Let x=amount of hours it takes 4 workers to pave 280 meters of road
If it takes 8 1/2 hours for 6 workers to pave 140 meters of road, then it takes (8 1/2)*6=51 worker-hours to pave 140 meters of road. This means that 1 worker works at the rate of (140/51) meters per hour; 4 workers then would work at the rate of 4*(140/51)=(560/51) meters per hour. Now our equation to solve is:
(560)/51)*x=280 meters
x=280*(51/560)=51/2=25 1/2 hours
CK
(560/51)*25 1/2=280
560/2=280
280=280
Hope this helps---ptaylor
RELATED QUESTIONS
If it takes 4 workers 6 hours each to pave a road, how many hours will it take 12... (answered by amoresroy)
It takes nine days for 8 worker to pave a stretch of road. If each worker works at the... (answered by Mathtut)
If a surfacing crew takes 167 seconds to pave 29 feet of asphalt, how many hours will it... (answered by solver91311)
It takes 3 men 5 days to pave one mile of road. How long would it take 2 men to pave 10... (answered by ewatrrr)
Please help me solve this equation: It takes 4 men 16 hours to pave a footpath. How long... (answered by richwmiller)
Each of two road graders can pave a certain section of the road in 15 hours working... (answered by stanbon)
It takes 20 workers a total of 30 days to pave a highway. How many days would it take 15... (answered by josgarithmetic,askhari139)
If a surfacing crew can pave five feet of asphalt per minute, how many hours will it take (answered by richard1234)
One road crew can pave a section of highway in 15 h. A second crew can do the same job in (answered by josgarithmetic,ikleyn,Alan3354,greenestamps)