SOLUTION: After a certain number of men had been employed on a job for 24 days and had finished half of it, 16 more men were employed and the remaining job was completed in 16 days. How many
Algebra.Com
Question 919789: After a certain number of men had been employed on a job for 24 days and had finished half of it, 16 more men were employed and the remaining job was completed in 16 days. How many men were employed first?
Found 2 solutions by ewatrrr, josmiceli:
Answer by ewatrrr(24785) (Show Source): You can put this solution on YOUR website!
24n = 16(n+16)
8n = 256
n = 32 men were employed at first
And...checking
32*24days = 48*16days
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
Let = number of men employed first
= the rate of working
for men
-----------------
= the rate of working for man
------------------
Then, 16 more men were employed and the
remaining job was completed in 16 days
For man, this is a rate of:
--------------------------
Now I can say:
32 men were employed first
--------------
check:
OK
RELATED QUESTIONS
A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were... (answered by josgarithmetic)
An MNC company hired 25 men to do a work in 32 days.After 16 days it employed 5 more men... (answered by richwmiller)
A contractor undertook a certain work to be done in 80 days and employed 72 men to do it. (answered by ankor@dixie-net.com)
A certain number of men can finish a piece of work in 10 days. If however there were 10... (answered by ankor@dixie-net.com)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
300 men were engaged to complete a job in a certain number of days. But due to another... (answered by richwmiller)
300 men were engaged to complete a job in certain number of days. but due to another... (answered by richwmiller)