SOLUTION: Three brothers,Michael,Matthew and Mark are tasked to mow a 2000 square meter garden. In 8 hours, Michael, the eldest, can mow 1200 square meters. Matthew can mow 600 square meters

Algebra.Com
Question 919307: Three brothers,Michael,Matthew and Mark are tasked to mow a 2000 square meter garden. In 8 hours, Michael, the eldest, can mow 1200 square meters. Matthew can mow 600 square meters and Mark, the youngest ca mow 200 square meters. If they work together for 5 hours, what part of the garden is not mowed?
Follow up question: with reference to the question above, suppose the three brothers worked together for 4 hours but Mark got tired and quit. Matthew stayed for another half-hour and quit. How long will it take to Michael finish the job?

Answer by Edwin McCravy(20065)   (Show Source): You can put this solution on YOUR website!
Three brothers,Michael,Matthew and Mark are tasked to mow a 2000 square meter garden...
'
In 8 hours, Michael...can mow 1200 square meters.

So Michael's mowing rate is 1200 square meters per 8 hours or 



In 8 hours...Matthew can mow 600 square meters

So Matthew's mowing rate is 600 square meters per 8 hours or 



In 8 hours...Mark...can mow 200 square meters.

So Mark's mowing rate is 200 square meters per 8 hours or 



If they work together for 5 hours,

Their combined mowing rate is  or  

Therefore in 5 hours they will have mowed  or 

what part of the garden is not mowed?
`
...a 2000 square meter garden.

So 2000-1250 = 750 square meters are no mowed.

-------------------------------------------------

Follow up question: with reference to the question above, suppose the three brothers worked together for 4 hours...

Their combined mowing rate is   

Therefore in 4 hours they will have mowed  or 

but Mark got tired and quit. Matthew stayed for another half-hour and quit.

Michael's and Matthew's combined mowing rate is  or .

Therefore in that half hour Michael and Matthew will have mowed  or 

So when Matthew quits, the number of square meters mowed is 1000+225+112.5 or
1337.5 square meters.

So there are 2000-1337.5 or 662.5 square meters unmowed. 

How long will it take to Michael finish the job?

Since Michael's rate is ,
and , it will take him  or 4 hours and 25 minutes.

Edwin

RELATED QUESTIONS

Three brothers,Michael,Matthew and Mark are tasked to mow a 2000 square meter garden. In... (answered by Theo)
Three brothers,Michael,Matthew and... (answered by richwmiller)
Michael can mow the lawn in half an hour, and Alex can mow it in three quarters of an... (answered by josgarithmetic)
Mr. Agbuya can mow a lawn in 3hours. His sons, Michael and Arnel can each do the job in... (answered by macston)
Michael can do a job 3 hours faster than Dennis. Together they can complete the work in 8 (answered by BlGDAVE,josgarithmetic)
41. Mr. Agbuya can mow a lawn in 3 hours. His sons, Michael and Ariel, can each do the... (answered by Edwin McCravy)
Michael can mow 2/5 of his yard in one hour. How many hours would it take for Michael... (answered by CubeyThePenguin,ikleyn,greenestamps,josgarithmetic)
sammy can mow a lawn in 3 hours. his two young brothers can each do the job in 2 hours.... (answered by KMST)
sammy can mow a lawn in 3 hours. his two young brothers can each do the job in 2 hours.... (answered by alma11,Alan3354)