SOLUTION: If it takes 6 men to complete a job in 12 days, how many men would it take to complete the same job in 18 days?
Algebra.Com
Question 911696: If it takes 6 men to complete a job in 12 days, how many men would it take to complete the same job in 18 days?
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
man-days 6*12=72
new number of days=18=18
man days needed/days 72/18= 4 workers needed
RELATED QUESTIONS
60 men worked 12 days on a job. How many men would it take to complete the same job in 8... (answered by nyc_function)
If it takes 64 men 15 days to complete a job, how many more men would be required to... (answered by Alan3354,richwmiller)
it takes 9 men to compete a job in 8days. How many men would it take to complete the job... (answered by ankor@dixie-net.com)
If it takes 8 men to complete a job
in 8 days, how many days would it take 1... (answered by stanbon)
if it takes 9 men 15 days to complete a construction job, how long would it take to... (answered by ankor@dixie-net.com)
If it takes 6 men to do a job in 4 days how many days will it take 2... (answered by oscargut)
If 12 men and 10 women can complete a job in 15 day, how many days will it take for 30... (answered by ikleyn)
if 8 men can do a job in 12 days how long will 24 men take to complete it
(answered by amarjeeth123)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)