SOLUTION: 60 people can finish a work in 15 days. After doing 6 days of work, 12 people added to the group for completing the same work. In how many days, they will complete the work?

Algebra.Com
Question 910610: 60 people can finish a work in 15 days. After doing 6 days of work, 12 people added to the group for completing the same work. In how many days, they will complete the work?
Found 2 solutions by ankor@dixie-net.com, richwmiller:
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
60 people can finish a work in 15 days
Find the no. of man-days required to complete the work
60 * 15 = 900 man-days
:
After doing 6 days of work, 12 people added to the group for completing the same work.
In how many days, they will complete the work?
Let x = no. days to complete the job after 12 more were added
60(x+6) + 12x = 900
60x + 360 + 12x = 900
60x + 12x = 900 - 360
72x = 540
x = 540/72
x = 7.5 additional days:
:
Confirm this
Original 60 worked 6 + 7.5 = 13.5 days
60 * 13.5 = 810 man-days
12 * 7.5 = 90 man-days
------------------------
total man-days: 900

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
man-days 60*15=900
man days worked=60*6=360
man days needed=900-360=540
new number of workers=60+12=72
man days needed/new number of workers 540/72= 7.5 days needed

RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
20 men can do a piece of work in 24 days. After working for 6 days, additional number of... (answered by richwmiller)
10 men can do a piece of work in 24 days. After working 6 days,few men were added to... (answered by Edwin McCravy)
If 8 people do a piece of work in 12 days, how many people will be needed to do the same... (answered by scott8148)
In One factory 12 people can do piece of work in 19 days. During first 4 days all 12... (answered by ankor@dixie-net.com)
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the (answered by stanbon)
Tom takes 3 days to do a piece of work while jerry takes only one day for the same.... (answered by ikleyn)
if a group of 15 person is required to work for 8 days to complete a project how many... (answered by josgarithmetic)
60 persons can complete a building in 250 days . after 200 days , work stopped for 10... (answered by ewatrrr)