SOLUTION: P can do a piece of work in 20 days and Q in 24 days. find how much time will they take to complete the work if they work alternately starting with P ??
Algebra.Com
Question 908456: P can do a piece of work in 20 days and Q in 24 days. find how much time will they take to complete the work if they work alternately starting with P ??
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
1/a+1/b=1/x
1/20+1/24=1/x
24/480+20/480=1/x
44/480=1/x
x=480/44
x=10.9090909 days working together
Double the time if they don't work at the same time
RELATED QUESTIONS
P can do a piece of work in 20 days and Q in 24 days. find how much time will they take... (answered by richwmiller)
if 800 people can do a piece of work in 80 days.after 5 days 50 people left.How much more (answered by josgarithmetic)
Ramesh , Suresh and Harish can do a piece of work in 15 days, 10 days and 6 days... (answered by mananth)
B will take 3 days longer than A to complete a piece of work. If they together can... (answered by richwmiller)
P can do a piece of work in 20 days and Q in 24 days. (answered by richwmiller)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
Pedro and Juan can do a piece of work in 3 and 3/7 days . If Pedro works in 3 days and... (answered by josgarithmetic)
John can complete a piece of work in 3 days. Jojce can do it in 9 days and James can do... (answered by ewatrrr)
a man does half as much work as his son in three - four of the time .if they take 18 days (answered by Theo)