Question 905931: a contractor decides that he can build a barn in 8 weeks using 5 men. if he employs 3 more men how long would the job take? assume that all men work at the same pace. math question answer needed
Found 2 solutions by Fombitz, ewatrrr:
Answer by Fombitz(32388)   (Show Source): You can put this solution on YOUR website!
man-weeks of effort needed.

It would take 8 men a total of 5 weeks.

Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!

t = 5weeks

RELATED QUESTIONS

A contractor estimates that he can paint a house in 5 days by using 6 men. if he actully... (answered by ankor@dixie-net.com)
A contractor undertakes to build a bridge 12 km long in 350 days and employs 45 men. At... (answered by josgarithmetic,MathTherapy)
A contractor estimates that he could finish a project in 15 days if he has 20 men. At the (answered by josmiceli)
A contractor engages 16 men to build a wall 80 metres long and estimated that they will... (answered by ewatrrr)
How do I figure this out easily?? A study shows that a contractor employs 6 times as... (answered by checkley79)
A Certain Job Can Be Done By 8 Men In 20 Days. After 5 Days, 3 Men Left The Job. How... (answered by Theo,Fombitz)
A 3-men crew can do a certain job in 3 weeks and 2 days, if we are to hire 4 men crew... (answered by josmiceli)
A contractor estimated that one of his two bricklayers would take 9 hours to build a... (answered by ankor@dixie-net.com)
3 men build a house in 10 days . how long would it take 5... (answered by ankor@dixie-net.com)